28 July, 2026

smart city and security infrastructure

The Srinagar Smart City Mission has completed 157 of 161 projects, with Rs 3,530 crore worth of work executed as of March 31, 2026

The Srinagar Smart City Mission has completed 157 of its 161 sanctioned projects as of March 31, 2026, with 98 per cent of the planned work now finished. The Government of India said projects worth Rs 3,530 crore have been executed against a total sanctioned cost of Rs 3,633 crore.

The update was shared in the Lok Sabha by Minister of State for Housing and Urban Affairs Tokhan Sahu in response to an unstarred question from MP Aga Syed Ruhullah Mehdi. According to the minister, the projects were planned at the local level following consultations with citizens and other stakeholders and approved by the State High Powered Steering Committee.

Projects Focus on Urban Development

The Srinagar Smart City Mission has covered several areas of urban development, including smart mobility, Water, Sanitation and Hygiene (WASH), smart governance, smart energy, and the environment. Srinagar Smart City Limited reported that 157 projects have been completed, while four projects remain pending.

The broader Smart Cities Mission aims to support locally driven urban development through projects designed around the needs of individual cities. The government said proposals are developed after consultations with citizens and stakeholders.

Waterlogging and Accountability Questions

The update came amid questions about waterlogging and flood-like conditions witnessed in Srinagar following recent rainfall. The query sought details on whether the Smart City projects included storm-water drainage, flood mitigation, and urban water management, as well as whether technical audits had been initiated to assess drainage infrastructure.

The ministry's response did not provide project-wise details on drainage or flood mitigation works, nor did it specify the causes of recent waterlogging. It reiterated that the projects address multiple urban sectors, including WASH.

On accountability, the government said audits of Smart City Special Purpose Vehicles are conducted by the State Auditor General under the Companies Act, 2013. The Ministry of Housing and Urban Affairs has also established a multi-level monitoring mechanism for implementing the Smart Cities Mission.

For official information, readers can visit the Ministry of Housing and Urban Affairs.

FAQs

1. How many Srinagar Smart City projects are complete?

A total of 157 out of 161 sanctioned projects have been completed as of March 31, 2026.

2. How much has been spent on the projects?

Projects worth Rs 3,530 crore have been executed out of a total sanctioned cost of Rs 3,633 crore.

3. What sectors do the projects cover?

The projects cover smart mobility, WASH, smart governance, smart energy, and environment-related initiatives.

4. How many projects remain incomplete?

Four of the 161 sanctioned projects are yet to be completed.

5. Are the projects being audited?

The government said audits of Smart City SPVs are conducted by the State Auditor General, alongside a multi-level monitoring mechanism established by the Ministry of Housing and Urban Affairs.